Thursday, August 26, 2010
Ground Floor slabs on
Finally we have the ground floor slabs on. They were lifted in yesterday, and another stage of the house is completed. It also helps us to get the real size of the rooms on this floor and many of these are the key rooms in the house as the most used. The added height of the ceiling (to make up for the step in the kitchen) is evident when you walk in, below the floor to ceiling height is not too far off 3.5 meters, this will come down by 400mm with floor and suspended ceiling. We can also start thinking of things such as kitchen layouts and other significant rooms that will effect parts of the build such as underfloor heating. We're still a good 3 weeks behind where I wanted to be, so the race is on to get weather tight - something I'm clearly obsessed with at the moment. The back rooms now seem dark - the concrete blocks don't reflect any light and we're used to having full daylight all over the rooms.
Window quotes still continue to come in. There is a range of quotes as you'd expect from a number of companies with products that appear similar. Some of the things I'm looking for are U-values (performance on insulation) and security - the first is important for us as we're at the edge of the heating system capability and anything we can claw back and save brings us closer to being able to work as is without adding extra heat pumps. The question will be how much of a premium that is worth, you spend pounds to save pennies over 20 years or so. Once that is resolved, then the next phases are pretty much lined up to the point where we can think of starting the interior fit out.
Finally the perspective picture view with these slabs on and the steel frame completed on the front windows.
Thursday, August 19, 2010
Slow going with blocks
The blocks are not going up anywhere nearly as quickly as we'd been sold. These internal walls will be carrying load for the hollowcore 1st floor, so we can't get these in place until they are completed. It's not a mis-estimation on the builders part, the issue is that the blockies didn't turn up for a few days, and I suspect didn't exactly do a full days work when they were there. These guys are subcontracted by the structure builder, so I don't have a direct line to them, and the builder isn't always on site while these guys are supposed to be, so supervision is minimal. At this stage with everyone complaining about the lack of work you'd think people would want to get through it and maintain a good name for the next job. I guess not.
This story is nearly finished, most of the blocks are up and hopefully this will then get slabbed next week. The final ICF row, internal blocks and then the roof (finally) can start. In the picture the columns are either side of the fireplace. We're looking to install a warm air circulation system, this is above the stove we'll fit here and allow air above it to get heated and circulate back out the top of the stack. This should improve the heat we obtain from the unit when its on. We still plasterboard over the area so this space is hidden, and we'll have to work out how to affix heavy items such as a TV etc. But combined with the Heat-Recovery ventilation we can use the stove to pump heat all around the house. It's located in the central open space, and warm air here will naturally circulate to the dining room, kitchen, back lobby and top landing. However, if we're in a position that we're depending on this for heat we're already in trouble!
Again I'm only worried about the pace of building from the perspective of getting the house sealed. We're getting quotes for windows, doors, stone and have plaster in mind, so if we get pushing we might have an intense 8-10 weeks to get weather tight and ready for internal fit-out.
This story is nearly finished, most of the blocks are up and hopefully this will then get slabbed next week. The final ICF row, internal blocks and then the roof (finally) can start. In the picture the columns are either side of the fireplace. We're looking to install a warm air circulation system, this is above the stove we'll fit here and allow air above it to get heated and circulate back out the top of the stack. This should improve the heat we obtain from the unit when its on. We still plasterboard over the area so this space is hidden, and we'll have to work out how to affix heavy items such as a TV etc. But combined with the Heat-Recovery ventilation we can use the stove to pump heat all around the house. It's located in the central open space, and warm air here will naturally circulate to the dining room, kitchen, back lobby and top landing. However, if we're in a position that we're depending on this for heat we're already in trouble!
Again I'm only worried about the pace of building from the perspective of getting the house sealed. We're getting quotes for windows, doors, stone and have plaster in mind, so if we get pushing we might have an intense 8-10 weeks to get weather tight and ready for internal fit-out.
Tuesday, August 10, 2010
Ground Floor internal walls
With the outside walls poured the work has started on the internal walls. Again we'll start to see the floor plan come to life and be able to walk though the house, allowing us to start planning the interior layouts in our own heads.
There are more and more detail decisions we need to make at this stage, that we really haven't thought of. Size of the opening for the stove, final ideas of room sizes, as well as starting to plan stone cladding, windows and cills. It'll be a busy period now as we make these choices, view work in other houses and order in materials and labour. On top of that the roof will hopefully be ready to be started in another 2 weeks. While that is going in, we want to be moving fast on all the other aspects - sills in, stone on, windows in or there-abouts and if we still have time maybe start the external render.
With the windows we'll end up with some problems. The large windows in the basement are too big to have as side-hung, so while we could have a tilt & turn window closing it may be very difficult due to the weight. The curved wall may either be segments or a curved pane- the latter may be very expensive. We also have to decide if we want certain pane's divided or left as single large panes. Thats all without deciding on colour and type.
We have a decision on the external stone - a natural stone cladding made up of quartz and granite. This has proved to be significantly cheaper than natural stone to apply - both in the cost of the stone and more so in the cost of the labour to fit it. We'll also need to sort out an installer for the sills - these require a bit more detail as damp-proofing needs to be installed as well.
Finally, we also have our first tenants in - a flock of swallows have built a nest in a girder inside the garage. They did it a lot bloody quicker than we managed as well. They'll be off for the winter, and hopefully when they get back there will be no way in for them. The carport area is exposed though, so we'll have to ensure there are no handy nesting spots - otherwise Lorraine can park her car under the nest and clean up the consequence!
There are more and more detail decisions we need to make at this stage, that we really haven't thought of. Size of the opening for the stove, final ideas of room sizes, as well as starting to plan stone cladding, windows and cills. It'll be a busy period now as we make these choices, view work in other houses and order in materials and labour. On top of that the roof will hopefully be ready to be started in another 2 weeks. While that is going in, we want to be moving fast on all the other aspects - sills in, stone on, windows in or there-abouts and if we still have time maybe start the external render.
With the windows we'll end up with some problems. The large windows in the basement are too big to have as side-hung, so while we could have a tilt & turn window closing it may be very difficult due to the weight. The curved wall may either be segments or a curved pane- the latter may be very expensive. We also have to decide if we want certain pane's divided or left as single large panes. Thats all without deciding on colour and type.
We have a decision on the external stone - a natural stone cladding made up of quartz and granite. This has proved to be significantly cheaper than natural stone to apply - both in the cost of the stone and more so in the cost of the labour to fit it. We'll also need to sort out an installer for the sills - these require a bit more detail as damp-proofing needs to be installed as well.
Finally, we also have our first tenants in - a flock of swallows have built a nest in a girder inside the garage. They did it a lot bloody quicker than we managed as well. They'll be off for the winter, and hopefully when they get back there will be no way in for them. The carport area is exposed though, so we'll have to ensure there are no handy nesting spots - otherwise Lorraine can park her car under the nest and clean up the consequence!
Monday, August 2, 2010
Steel up
With the steel now in around the windows and lower floor area the pace is back up. Hopefully we'll be in a position to pour the walls of the next story Tuesday, and then it'll be a sprint to get the internal blocks up - these are needed to support the weight of the hollow-core floors above. All in all we still may make it for the 3rd week in Aug to get to roof plate - once these slabs go up then there is only a section of ICF left to go as well as internal walls, and no details with steel for load bearing left. Given that, ideally the roofer will start then while the stairwell is cast.
It's about 2-3 weeks off where I wanted to be at the start, we've had a lot of little niggle delays, mostly around specification and detail of areas that ideally would have been thought out to start with. It's meant that we've had to go back and retrofit steel, penetrate the hollowcore floors and a few other things like that that make you roll your eyes a bit. I'm all for getting sleeves rolled up and get moving, but a bit more thought on the engineering may have saved me a good few thousand euro by being rolled into the original cost and thus open for negotiation. While the extra detail prices aren't exorbitant, its difficult to negotiate the prices as you've been locked into the builder for that section.
We also had a stonemason looking at the site as we've decided on what stone to use. It's a natural stone cladding (comes in tile-like sections) but is made of natural stone. The one we've picked is mostly quartz - its what we've been drawn to in the stone yards and I think the natural sheen on the stone will make it very changeable in the light. We're also looking at internal walls where we may put stone - we're thinking of a grey slate in some areas of the basement. Give that cave feel.
Windows are still not even quoted - there has been a big hold up in getting a proper window schedule, with designated fire hinges or toughened glass where required for regulations. Not a massive blocker now, but we're now into the builders holidays and a lot of firms will be shut up for these 2 weeks. It's all getting tight to get closed up by end of October.
It's about 2-3 weeks off where I wanted to be at the start, we've had a lot of little niggle delays, mostly around specification and detail of areas that ideally would have been thought out to start with. It's meant that we've had to go back and retrofit steel, penetrate the hollowcore floors and a few other things like that that make you roll your eyes a bit. I'm all for getting sleeves rolled up and get moving, but a bit more thought on the engineering may have saved me a good few thousand euro by being rolled into the original cost and thus open for negotiation. While the extra detail prices aren't exorbitant, its difficult to negotiate the prices as you've been locked into the builder for that section.
We also had a stonemason looking at the site as we've decided on what stone to use. It's a natural stone cladding (comes in tile-like sections) but is made of natural stone. The one we've picked is mostly quartz - its what we've been drawn to in the stone yards and I think the natural sheen on the stone will make it very changeable in the light. We're also looking at internal walls where we may put stone - we're thinking of a grey slate in some areas of the basement. Give that cave feel.
Windows are still not even quoted - there has been a big hold up in getting a proper window schedule, with designated fire hinges or toughened glass where required for regulations. Not a massive blocker now, but we're now into the builders holidays and a lot of firms will be shut up for these 2 weeks. It's all getting tight to get closed up by end of October.
Subscribe to:
Posts (Atom)