So I got a little bored with blogging and somehow left it slip from Nov. But in the meantime I've been busy with the project and there is a lot of changes (thankfully)!
Internally the plastering is pretty much complete. I had some areas that were leaking (where there are flat roofs) and these are still left bare with plasterboard, and the front porch area is un boarded - but the rest of the house is skimmed and the rooms look like they're almost finished!
This really squares up the interior walls and the eye now has clean lines to follow. Above is on the landing upstairs looking at the door to the master bedroom, we've a nice spot right there for a seat under the Velux - perfect spot for some reading.
In Dec I pretty much took a few weeks off to enjoy Christmas party season, much needed after a bit of a slog to this point. Once the 27th hit it was time to get the floor insulation in. With underfloor heating we have to have a serious amount on the floor and we installed 125mm Xtratherm PIR on the basement and ground floors. It's not too technical, so an unskilled lad like myself gave it a go. Straight away you get to see all the imperfections for yourself, where walls aren't as straight as the machine cut insulation. I laid the insulation, foamed the joints where there was any gap. On the two grounded floors I also put a 25mm thick upstand - this is a piece of insulation that will separate the finished floor slab and the rising walls to prevent the slab from heating these up too much. Since they connect straight to the un-insulated sub-floor this would be an easy way for heat to escape! I had the underfloor heating plumber booked in, and while I thought I'd have enough time I ended up taking a week off work extra and pulling 12-14 hr days with portable lighting.
My camera phone is getting worse with the concrete dust taking its toll on the lens! You can see the central vacuum tube on the right with the insulation undercut to fit on top, on the left is the underfloor heating flow/return to the ground floor. These pipes really took up a lot of extra time!
With this done I pulled in a few extra hands to get a polythene sheet layer on top - this layer does a few things
Internally the plastering is pretty much complete. I had some areas that were leaking (where there are flat roofs) and these are still left bare with plasterboard, and the front porch area is un boarded - but the rest of the house is skimmed and the rooms look like they're almost finished!
This really squares up the interior walls and the eye now has clean lines to follow. Above is on the landing upstairs looking at the door to the master bedroom, we've a nice spot right there for a seat under the Velux - perfect spot for some reading.
In Dec I pretty much took a few weeks off to enjoy Christmas party season, much needed after a bit of a slog to this point. Once the 27th hit it was time to get the floor insulation in. With underfloor heating we have to have a serious amount on the floor and we installed 125mm Xtratherm PIR on the basement and ground floors. It's not too technical, so an unskilled lad like myself gave it a go. Straight away you get to see all the imperfections for yourself, where walls aren't as straight as the machine cut insulation. I laid the insulation, foamed the joints where there was any gap. On the two grounded floors I also put a 25mm thick upstand - this is a piece of insulation that will separate the finished floor slab and the rising walls to prevent the slab from heating these up too much. Since they connect straight to the un-insulated sub-floor this would be an easy way for heat to escape! I had the underfloor heating plumber booked in, and while I thought I'd have enough time I ended up taking a week off work extra and pulling 12-14 hr days with portable lighting.
My camera phone is getting worse with the concrete dust taking its toll on the lens! You can see the central vacuum tube on the right with the insulation undercut to fit on top, on the left is the underfloor heating flow/return to the ground floor. These pipes really took up a lot of extra time!
With this done I pulled in a few extra hands to get a polythene sheet layer on top - this layer does a few things
- Separates the concrete from the insulation - the acid in the concrete can corrode the PIR
- Vapor layer - the difference in temp above/below the insulation can cause condensation
- Protect the plasterboard - the water in the concrete won't be good for the plaster
We blitzed the house in a couple of nights and had it all ready for the plumber. We also fashioned the step in the kitchen - this was previously all the same level. First we fashioned a plywood curve, buttressed with wood to ensure it will take the weight of the concrete. Next we barrowed in 20 tonnes of crusher dust from a nearby quarry, leveled it to 220mm and then used a whaker to compact it. Floor insulation and polythene and we had enough for 70-80 mm concrete screed on top.
Next in was the UFH pipes, a week of rolling this out and installing the manifolds for their plumber and its done. We had the floor screed guy booked in straight after, I was pretty nervous about the idea of damage to these pipes.. once they're in its a nightmare to excavate and fix. Thankfully no major problems and the screeder was ready literally the next day the plumber finished.
While he was there we were broken into - small window broken and since there is nothing of any value left on site nothing was robbed. They did mange to get at some of the electrical cable ends, shortening them some. Its left a headache for the electrician as all the tail markings are gone - he has to go and figure out which cable is which all over again.
Screeding went without a problem and we were into February. Feb was mostly about getting ready for ESB connection, finishing groundworks, arranging electrical certs and building the vault for the connection. We had laid the duct before but I had to terminate the end neatly at the pole. The 125mm duct gets stepped down to 50mm at the house, and between these sizes I built a block walled vault with an ESB manhole. First time building block and lets just say I'm not going pro, but it'll be all underground and hopefully never seen again. The ESB connection went without a hitch - its great having full power on site without needing a generator.
Next up was water. We had the well driller survey and water divine the site - his father has the power. I was pretty confident with all the early water issues that we wouldn't be stuck for the stuff. Sure enough he drilled in 300ft with a good depth of water in there. With the well drilled then the pump was next - it was really interesting installing this, 91 meters down into the ground. That is half the height of the hill we're on top of! The pressure vessel was installed next to it.
There is a good stream of clear water, no smell and sure I had to give it a taste! I'm still alive -if this is what you call living.
I put 50mm insulation under all this and a 1sq mtr block wall (slightly better than my first attempt!) I'll insulate the walls and build a hinged lid - the insulation may help when in winter I'll probably run a IR heat lamp in here to stop any joints freezing up. Straight after we ran power up to the unit, and the plumber has routed the output to the basement.
On the same week I've had fiberglass installed all around the flat roof join to keep out any water - hopefully this is the end of that and I can get the inside finished off! Its a really neat job and cleans up this area. We'll install paving or some covering on this, so this isn't the finished surface.
Thats where we are - next stop is getting the heating components installed, filling the underfloor and Solar and getting the heatpump installed. Meanwhile we're trying to design kitchens, have ordered stone to dress the stairs and are trying to find a handrail for it.
The remaining issue is the outside plaster. When we fitted it the conditions were fine, however 4 days later its started to wash off. We're trying to get the supplier to take responsibility for the product not performing.