Finally the stairs is complete - the sage of this has been a bit of torture, and has held up a lot of the work that needs to be done over the next week - that will then allow some parallel work to take place. The concrete will be finished off with a stone cladding on the topside and plastered underneath.
With this in place the windows can be installed and the roofs tanked giving us a weatherproof house (bar the front door and 1 window) and plumbing 1st fit can begin next week. There are some changes in the design that will effect the plumbing, a bit of concrete slab chiseling will be required as well as getting out to the outside for waste pipes. These will have to be carefully sealed afterwards to prevent future air and water ingress.
So plan for the next week:
Thursday - Window install
Wed -> End June - Roofs tanked
Sat - mark out the plumbing areas and get cutting the concrete, seal off the front door area with timber to prevent access.
Next week start 1st fit plumbing.