Monday, June 21, 2010

2nd Foundations poured

With excellent weather there has been no reason to hold back and with the last of this section of groundworks completed it's a blessing with no delays for rain or the tracked vehicles tearing up the surface.  It's dry and compacted all over the next build area.  With a few days left of the sunshine forecast, hopefully we can get a solid start on the ground floor walls and bring up the house another level.



The changes to the walls mean that we owe our builder a revised drawing, I prefer he demands that rather than winging it, but any reason to stop is painful.  Hopefully our architect can jiggle these in CAD over the weekend and we can get started.  Neither of us can wait to step into the next floor, and no doubt the room sizes will be a topic of discussion.  If we're lucky, we could see the next 2 floors on within the month.